Sign In

Resources

 

FAQs


Applications

When are Public Facilities applications due?

  • The LCDBG Public Facilities Program has a two-year funding cycle, which is divided into two phases.  In Phase I, Project Severity packages were accepted for FY 2020 and FY 2021 LCDBG Public Facilities Program on July 12, 2019.  No additional Project Severity packages will be accepted for this funding cycle.  The packages were reviewed and scored.  In Phase II, the applicants whose severities ranked in the top 60% of these scores were invited to submit a full application providing that they met threshold criteria as of July 12, 2019 for the FY 2020 program year.  Applicants will have to meet the past performance threshold criteria be July 10, 2020 for the FY 2021 program year.  Invitations to submit full applications for FY 2021 are anticipated to be sent out in August 2020.


Civil Rights

When preparing the “Contract and Sub-Contract Activity Form” (formerly the MBE), should every contract be listed for each grant?

  • No, only list those contracts (construction and/or non-construction) that were awarded since the last reporting period.  For example, if a contract was awarded and reported during a previous cycle, it should not be reported again.

What are some ways to show a “Good Faith Effort” has been made to ensure compliance with Section 3?

  • An extensive list of examples can be found in the FY 2019 Grantee Handbook on pages 61-63.  Remember that all efforts must be documented.

Are Tables A and B required for all sub-contractors?

  • No, Tables A and B are only required for sub-contractors whose contracts are greater than $100,000.00.  However all sub-contractors, regardless of contract amount, are required to complete a "Section 3 and Segregated Facilities Certification", found on page 209 of the 2019 Grantee Handbook.

What amount goes in Box 3 on Page 1 of the Section 3 Summary Report in the closeout documents?

  • This box should reflect the amount that has been or will be spent, not necessarily grant amount.  Boxes 1A and 2A on page 2 should also indicate the actual amount that will be spent.          


Community Development (CD) Plan

What should be included in the CD Plan?

1.  Period of applicability.  This covers the three-year period of the grant.  The period begins when the Grantee has been given authorization to incur costs. 
2.  Needs of the community.  Also note if there are any population groups experiencing high rates of unemployment.  If there are none, include a statement to that effect.  
3.  Data sources.
4.  Strategy that addresses the community’s needs.  Include objectives, activities, timing, monetary amounts, and potential sources of funds (LCDBG as well as other sources).

  • Use the information gathered to write the CD Plan, being careful to adhere to the form’s outline as well as the official instructions contained in the Community Development Plan exhibit of section A in the Grantee Handbook


Engineering

Change Orders

What is the order that I need to get a Change Order signed?

  • All LCDBG Change Orders must utilize the following procedure;

1.      The engineer & the contractor sign and date the C.O.
2.      Submit the C.O. to the LCDBG Engineer by email or mail.
3.      The LCDBG Engineer will approve the C.O. and email it back to the consulting engineer.
4.      Get the Mayor or Parish President to approve with date of signature.


 If a Change Order is for Time Only, do I need to submit the Change Order to OCD-LGA?

  • Yes, all Change Orders must be submitted to OCD-LGA. 

If the LCDBG grant money is depleted and a Change Order is to be paid for out of local funds, do I need to submit the Change Order to OCD-LGA?

  • Yes, it is still under the LCDBG contract so the Change Orders must be submitted to OCD-LGA.


Addenda 

If an Addendum is just an updated Wage Rate, do I need to submit the Addendum to OCD-LGA?

  • Yes, all Addendums must be submitted to OCD-LGA.

 

If an Addendum is just setting a new Bid Date, do I need to submit the Addendum to OCD-LGA?

  • Yes, all Addendums must be submitted to OCD-LGA.

 

Plans and Specifications 

Can I submit Plans and Specifications electronically?

  • No, hard copies of plans and specifications must be submitted.


Can I submit half-sized plans when I submit plans and specifications?

  • Yes, as long as all text and details are sized up for half-sized plans and are legible.

 

Engineering Fees 

Why are topographic survey fees not allowed under LCDBG Projects?

  • Topographic Fees are included in the Basic Services fee in the Engineering Fee Schedules and Policies for LCDBG.

 

Notice of Contract Award

What amounts should be listed on the Notice of Contract Award?

  • The Notice of Contract Award is strictly to notify the office of the amount of the construction contract with the contractor's name and information regarding the grant.  Only the amount of the construction contract should be included.  There should be no engineering fees or contingencies listed.

 

Resident Project Representative

What is the new process to qualify a Resident Project Representative?

  • The Qualification Certification for Resident Project Representative form from the Grantee Handbook, along with a copy of the Resident Project Representative's current resume showing qualifications and work history, must be submitted to the OCD-LGA engineer.  In order to qualify a Resident Project Representative (RPR), the applicant must have experience as a construction inspector, construction manager or construction field administrator.  If approved, the OCD-LGA engineer will send the approved Certification back to the Consulting Engineering.  If approved the OCD engineer will add the RPR name, date approved and name of the Consulting Engineering firm to the QPR - Qualified Resident Project Representatives spreadsheet.  After a Resident Project Representative is qualified, there is no need to resubmit the certification or resume.

 

Severity

 

Why is my Severity Score low? / How do I get a high Severity Score

I would have to review the specific Severity package to give an accurate answer but for most severity packages they receive a low score due to lack of documentation.   Severity Scores are generally based off the amount and variety of supporting documentation enclosed in the Severity Package.   It's not enough to say there are Citizen Complaints.  Copies of the complaints must be included in the Severity Package.  If there are Work Orders that support the severity claim, copies of the Work Orders should be included in the Severity Package.  Other supporting documentation, if applicable should be included in the Severity Package; Administrative Orders, Compliance Orders, Purchase Orders, Newspaper Articles, Social Media Posts, Legal Actions, etc.


Environmental Review Record (ERR)

When should the ERR be submitted?

To ensure that the State has sufficient time to review the ERR for completeness and to allow adequate time to revisions, the ERR must be received by the  State within four calendar months of the date of the authorization to incur costs letter.  The Grantee must receive permission for the OCD to publish either the Notice of Intent to Request Release of Funds or the Combined Notice within five months of the authorization to incur costs letter.

When and/or why should an extension be requested?

A request for extension should be submitted to the OCD prior to the ERR submittal deadline.  A request for extension should be made when the deadline  will be missed due to unforeseen circumstances such as late response times from agencies.  The request should include the reason that the extension is  needed.  The request should also include dates, such as when the ERR process began, when letters were mailed, and when responses were received.   

What does “wetland adjacent” mean?

A project is “wetland adjacent” if the project shares a border with a wetland.

What is the difference between site specific and area wide?

The project description and the map must indicate whether the ERR is site specific or area-wide for public facilities projects.  For a site specific project, the  project description and the ERR map would note the particular site.  A site specific map would indicate the streets or specific lines where work is being  done.  If the exact location of the project has not been determined, however, it is necessary to clear the entire project area.  Only the boundaries of the area need to be marked on the map.  If a project is cleared as site specific and the project site/location or scope of work changes from what was originally cleared, an amendment to the ERR is required and must be submitted to the OCD for review.

What agencies should be contacted?

Completion for the Statutory Worksheet is the first step in the ERR process.  The worksheet will indicate which, if any, agencies should be contacted for comments.

What if there is more than one person listed as a contact for the same Indian Tribe?

Each person listed on the HUD website as a contact must be contacted, regardless of whether they belong to the same tribe.

What if FEMA does not have a flood map for the area being cleared? 

For those areas that FEMA has developed preliminary maps, HUD has indicated that these should be used.  If FEMA has not published flood maps or  developed preliminary maps of the area, the grantee must make a finding based on best available data, such as the municipality/parish engineer, or local  Flood Control Agency.

 

Financial

When and how should an audit be submitted to the OCD?

An audit or financial report is required annually from each grantee within six months from the grantee's fiscal year end.  Once the report has been submitted to the Louisiana Legislative Auditor, notification can be e-mailed to Janelle Dickey.

 Do Financial Management Questionnaires (FMQ) need to be updated?

Yes.  An FMQ should be updated anytime there is a change in authority or responsibility.  It should be sent to OCD by mail.  Requests for Payment cannot be processed unless the signatures on it match those on the FMQ.

When will a deposit be made for a Request for Payment (RFP) that was submitted?

RFPs are first processed by the OCD and then sent to the Office of Financial Support Services (OFSS), which makes the payments to the grantee.  The deadline for OFSS to receive the RFP is Thursday in order for funds to be available in the grantee's account the following Friday.

How can I see if a payment was made?

Go to the OSRAP Vendor Search page, enter the grantee's Federal Employer Identification Number, select the payee, add filter information if needed, and then click "find payments."  Payments that have been made can be sorted by date to make the search easier.  Click on the Check/EFT Number to see detailed information about the payment.


 

Labor

How do I obtain a wage decision?
Go to www.wdol.gov and “Selecting DBA WDs.”  You can then browse by a list of states/territories.  Choose Louisiana, and then find the correct parish in the list provided.  The wage decisions are separated into the four major categories (Building, Heavy, Highway, and Residential).

Which wage decision do I need?
As mentioned in the Grantee Handbook, the local government has a “ten day responsibility,” which is to ensure that the wage decision(s) that is in effect ten days prior to the bid opening is part of the original bid package (or becomes part of the package via addendum, which must be sent to all who obtained a bid package).  Note: the “Ten Day Call” (an exhibit in the Labor section of the handbook) is no longer an LCDBG requirement.

Can I award a construction contract to a prime contractor prior to receiving clearance from LCDBG?
Yes.  While it is normal to receive contractor clearance prior to contract award (via an executed Verification of Wage Decision and Contractor Eligibility form; an exhibit in the Labor section of the handbook), LCDBG allows contracts to be awarded prior to this provided the award is made “contingent upon” approval/clearance by this office.

Once a contract is awarded, how quickly must I submit it to LCDBG?
The Notice of Contract Award (which is an exhibit in the Labor section of the handbook) must be submitted to LCDBG within 30 days of the award date.  Failure to do so will result in a finding when the monitoring visit takes place.

If an additional classification is needed for the project, what is the process?
To request an additional classification for the project, the HUD 4230A form must be submitted to LCDBG.  For instructions on exactly how to fill out the form, please see “Additional Classifications” in the Labor section of the handbook, as well as the instructions in the exhibit.

When interviewing employees on the job site, whom/how many do I have to interview?
You must interview all prime contractors, any subs whose contract is $100,000 or more, and any subcontractor that has a large number of payroll problems.  Additionally, you should interview any subcontractors that are present during the time of the interviews.  You must interview half of the laborers and at least one of each other classification present on the jobsite that day.

Do the contractors have to use the HUD WH-347 payroll form, or can they use their own version of a payroll form?
No, contractors are not required to use the WH-347 payroll form.  However, it is strongly recommended that they choose to do so.  If the contractor chooses to use their own payroll form, all required items from the HUD WH-347 must be included, including the “signature page” of the WH-347 (called the Statement of Compliance), which must be verbatim.  The WH-347 is a standard, straightforward form that contains all information needed by LCDBG (and HUD/DOL) and it can be found in the exhibits of the Labor section in the grantee handbook, as well as on DOL’s website (www.dol.gov).  See the Labor section of the handbook for more guidance on payrolls and how to complete them.

If there are underpayments on the project, does that mean there will be a finding once LCDBG monitors the grant?
Not necessarily.  If, during monitoring, LCDBG is the one who discovers the underpayment, then it will result in a finding.  However, if the consultant discovers the finding prior to the monitoring visit, and the process of restitution is underway at the time of the monitoring visit, then the result will not be a finding.  If the restitution process is still ongoing at the time of monitoring, then there will be an area of concern in the monitoring letter.  If the restitution process is complete, and all restitution has been paid at the time of monitoring, then there is no finding nor area of concern, and LCDBG considers the issue resolved, as the normal, expected procedure is being followed (consultant discovers underpayment and completes the restitution process).

If there are CWHSSA (overtime) violations, is restitution all that is needed, or are there additional penalties associated with those types of underpayments?
There are additional penalties.  For CWHSSA violations, in addition to restitution being paid, there are also “Liquidated Damages,” which is a pre-determined penalty assessed by HUD.  That penalty is $25 per worker, per day for overtime violations.  For example, if two workers were underpaid for overtime for two days, then the resulting penalty for liquidated damages will be $100; $25 per worker (two workers), per day (two days).  All payments for liquidated damages must be paid via wire transfer.  For most cases, the violating contractor can request a waiver from HUD for the penalty and HUD will generally grant the waiver (if it believes the error was an unintentional mistake).  However, if HUD believes that this error was made intentionally, or if there are previous instances in which the violating contractor has made the same error, HUD may choose to not grant the waiver (in which case liquidated damages must be paid via the wire transfer).  Please refer to the Payroll review Flowchart in the exhibits of the Labor section of the handbook for an overview of this process, as well as the “Corrective Actions Regarding Labor Standards Violations” part of the Labor section for further guidance.

If there were underpayments of any kind, when/where must that be reported?
Any restitution from the project must be reported on the Final Wage Compliance Report, which is part of the closeout documents, which can be found in the exhibits of the Monitoring and Closeout section of the handbook.  Additionally, if restitution for the project reaches $1,000 or more for any contractor or subcontractor, a Labor Standards Enforcement Report (an exhibit in the Section B of the Grantee Handbook) must be submitted to LCDBG once the corrective actions have been completed.

Workshops


FY 2021 Application Workshop PowerPoint Presentation



Our most recent Technical Assistance workshop was held on Jan 28-30.  Please see the presentation for procurement and citizen participation procedures here.



Helpful Links 

 

Acquisition and Relocation

Real Estate Acquisition and Relocation (HUD site)

Civil Rights

Fair Housing and Equal Opportunity (HUD site)

Community Development

Code of Federal Regulations

24 CFR Part 570.480 - Subpart I

Federal Register

Poverty Data by Census Tract

Economic Development

Standard Occupational Classification (U.S. Department of Labor site)

U.S. Census Bureau - North American Industry Classification System (NAICS)

Louisiana Economic Development (LED)

Environmental

HUD Region VI ERR Guidebook

Tribal Assessment Directory Tool (HUD)

FEMA's Flood Map Service Center

U.S. Fish & Wildlife Service Wetlands Mapper

Office of Coastal Management Coastal Zone Boundary Map

Sole Source Aquifers (EPA)

Endangered Species (FWS)

Air Quality (EPA)

Airport Hazards

Contamination and Toxic Substances: NEPAssist and EPA Envirofacts 

Additional Links

American Factfinder

Dun & Bradstreet-DUNS Numbers

HUD Guidelines for Conducting Income Surveys

Rural Development (USDA)

Rural Federal Funding Database